Description

River’s Edge Walking Trail Phase III will begin where Phase II extension ended at Harbor Lake Drive cul-de-sac and run parallel to Fairway Overlook. The trail is just shy of one mile.

October 2024: Trail design revisions are anticipated for erosion control and water runoff.

September 2024:  Clearing work along the planned trail continues with Pride Contracting.

August 2024: Pride Contracting Inc. started clearing trees and vegetation from the pre-determined trail path.

July 2024:  A survey is underway to determine the location of the trail. The design documents have been submitted to the Georgia Department of Natural Resources for review.

June 2024: The Clayton County Board of Commission awarded Pride Contracting, Inc. the $2.2 million contract to construct River’s Edge Walking Trail Phases 3 & 4 on June 4, 2024.

A notice to proceed will be issued to the contractor the first week in July.

May 2024:   Bids have been received and evaluated by the county. A vendor is expected to be awarded the project on June 4, 2024.

April 2024:  The invitation to bid is published and will close on April 29.

March 2024:  A solicitation package has been posted and a pre-bid conference and site visit with potential contractors will be held on April 4. The deadline to submit a bid for the project is April 25.

February 2024:  Prime Engineering has provided complete construction documents for the project. Planning, Design and Construction is working with Central Services to solicit bids for the project.

Budget

$5 million

Commission District

District 2

Served by Commissioner

Commissioner Felicia Franklin