Description
River’s Edge Walking Trail Phase III will begin where Phase II extension ended at Harbor Lake Drive cul-de-sac and run parallel to Fairway Overlook. The trail is just shy of one mile.
October 2024: Trail design revisions are anticipated for erosion control and water runoff.
September 2024: Clearing work along the planned trail continues with Pride Contracting.
August 2024: Pride Contracting Inc. started clearing trees and vegetation from the pre-determined trail path.
July 2024: A survey is underway to determine the location of the trail. The design documents have been submitted to the Georgia Department of Natural Resources for review.
June 2024: The Clayton County Board of Commission awarded Pride Contracting, Inc. the $2.2 million contract to construct River’s Edge Walking Trail Phases 3 & 4 on June 4, 2024.
A notice to proceed will be issued to the contractor the first week in July.
May 2024: Bids have been received and evaluated by the county. A vendor is expected to be awarded the project on June 4, 2024.
April 2024: The invitation to bid is published and will close on April 29.
March 2024: A solicitation package has been posted and a pre-bid conference and site visit with potential contractors will be held on April 4. The deadline to submit a bid for the project is April 25.
February 2024: Prime Engineering has provided complete construction documents for the project. Planning, Design and Construction is working with Central Services to solicit bids for the project.
Budget
$5 million
Commission District
District 2
Served by Commissioner
Commissioner Felicia Franklin